Transfer switch alternative
The person that came up with that idea has saved homeowners alot of money. Square D is the only brand I have seen them available for. They will work on the QO and Homeline series. The Homeline models are contractor grade loadcenters to compete with other brands. The QO series has been around for years. The lockout device will only work on QO models that the main breaker is mounted horizontial. If you have a QO loadcenter with a main breaker mounted verticle, you are out of luck.
The breaker used for the generator has to be in the top right two spaces of the loadcenter. The only part that makes you wonder how it got approved is the fact that it only works properly if the panel cover is secured to the panelbox. The lockout is mouted to the cover only. If the cover is off it is possible to have both breakers on at the same time.
If you plan to purchase one, keep in mind that you have to know if you have a Homeline or QO and also if it is for indoor or a outdoor loadcenter. The device is not universal.
|
|
Add Photo
Bookmarks: |
|
|
|
Transfer switch alternative
My comment about the panel cover being off is for the folks that have not used this device before. Have you ever been taking a cover off and while sliding the cover away from the wall you hear a breaker trip. You automatically set the cover down and reach back over and flip the tripped breaker back on. For those that are unfamiliar may flip the wrong breaker because now there is no lockout device to keep it from happening.
Numerous times I have been asked to make up a cord with two male ends. Now that's an accident waiting to happen!
|
|
Add Photo
Bookmarks: |
|
|
|
Transfer switch alternative
ncrunch32,
As you mentioned the time the power could remain off is the issue most can't afford. It's not the cost of material or labor.
One issue that some do not realize is the existing type of cable used between the meter and panel box (3 wire) has to be changed to a different type (4 wire)when the transfer switch is added in between.
Now you add in that the existing panel and meter base may not be back to back. Because of code changes from the time the house was built to the day you are ready to add the wiring for a gen. set may cause a lot more work than most realize.
Permits, scheduling the utility to turn the power off, the electrician to do the work, scheduling the inspection department to inspect the work, the utility getting back to install the existing meter, everything better go as planned to make this happen all in one day.
Where we work it is the inspection departments that hinder the one day deal. They won't let us schedule an inspection at a certain time during the day. You have to call the day before to set up an inspection, you call at 8:30 am the morning of the inspection to find out what number you are. You could be number 1. That means they will be there in about 15 minutes. When you hear that you know the homeowners are going over night without power. If you are a high number that means they won't be inspecting until late in the day, that doesn't give the utility any time to do their work after the inspection.
|
|
Add Photo